Materials on site

Paid for once, recovered automatically

Materials delivered but not yet built in still have to be paid for, then recovered as the work is certified. Doing that from memory is how a contractor ends up paid twice for the same brick.

30 days free · No card required · Every feature on every plan

Record it against the line it belongs to

An advance floating loose in a spreadsheet is a number waiting to be forgotten. Linking it to the bill line it relates to is what makes recovery automatic instead of manual.

Once linked, QScope knows that when that line is certified, part of the money has already been paid.

  • Description, quantity, rate and total, like any other priced item
  • Linked to the bill line the materials relate to
  • Status from provisional through confirmed to paid
  • Prints on your letterhead as an advance payment notice
Advance Payments
AP-01 Structural steel on site
Relates to2.02 Structural steel frame
Date issued12 Jun 2026
StatusPaid
Advance value, excl VAT£12,500.00
VAT at 20%£2,500.00
Total paid£15,000.00

Recovery happens as the work is certified

You do not track it. As the linked line is valued in following certificates, the advance is drawn back automatically, and the certificate shows what is happening rather than hiding it inside a total.

  • Recovered in proportion to the work certified on that line
  • Shown on the certificate as a note against the line, not buried
  • Outstanding balance visible at any time
  • Any remaining advance carried into the final account
Client Valuations
Recovery on PC-04
2.02 Structural steel frame, 62% certified£18,600.00
Includes advance £7,800.00 for materials on site
Advance value£12,500.00
Recovered to date(£7,800.00)
Outstanding£4,700.00
Questions

What surveyors ask before they start

Is an advance the same as a variation?

No. A variation changes the works. An advance pays early for works already in the contract, because the materials are on site and the contractor has bought them. It does not change the contract sum.

Does retention apply to an advance?

It follows your contract. Many contracts do not retain against materials on site, since retention secures workmanship rather than delivery. Set it to suit the terms you are working under.

What if the materials are never built in?

The advance stays outstanding and carries into the final account, where it is settled with everything else. Nothing disappears quietly.

Can I issue an advance payment notice to the client?

Yes. It prints on your letterhead with the description, the quantity and rate breakdown, the VAT and the total, ready to issue.

Related

The rest of the commercial picture

Try it on your next valuation

Not your whole portfolio. One live job, one certificate. If it does not save you time the first time you use it, walk away and take your data with you.