You enter one date. QScope returns the other three, for your contract form, with weekends and UK bank holidays already excluded.
5 min read · All help topics
Everything is counted from the due date, which you set on the certificate. Your contract decides what the due date is, usually by reference to a valuation date or an application.
QScope excludes Saturdays, Sundays and UK bank holidays from the counts. This is where hand counting normally goes wrong, and it goes wrong predictably around Easter and the August bank holiday.
Amended forms are common and a bespoke payment period overrides the standard one.
One job you can hold in your head. Nine jobs across three surveyors is where a notice goes missing, and it is never the project you were thinking about that morning.
The four dates print on the face of the document, together with the statement of the sum considered due and the basis on which it is calculated.
That statement is not decoration. Section 110A of the Construction Act requires a payment notice to give both the sum and the basis, and a certificate carrying only a total is weaker than one carrying the valuation behind it.
It does not check that the contract form you selected is the one that actually applies to your job, and it does not tell you whether a notice is valid. It calculates dates from what you entered.
The notices you issue remain your professional work and your professional responsibility. Keep your own diary of critical dates as well. A second record costs nothing.
Write to support@qscope.co.uk. Include the project reference and, if it is about a figure, the certificate number. Answers within one working day.
Not your whole portfolio. One live job, one certificate. If it does not save you time the first time you use it, walk away and take your data with you.